Work in Progress

Re: Work in Progress

Postby lady anorak 12 » Thu Jul 27, 2017 4:54 pm

Wow given the weather of yesterday you have got a lot done great to see the progress
Glynnis Frith
lady anorak 12
 
Posts: 105
Joined: Sun Apr 26, 2015 8:04 pm

Re: Work in Progress

Postby g.89 » Sat Jul 29, 2017 7:28 pm

Today, Saturday 2th, was a lovely day at Fimber Halt. Lots of sunshine and no showers!

Our youngest volunteer, Brad, got to work on VB3 removing rust and old paint from the steels and giving a coat of primer.
P1110275.jpg
Brad makes a start on the van steel work

Chris did some very hard work breaking up badly damaged concrete carriers.
P1110282.jpg
You probably cant see them but he's wearing ankle shackles as well!

Robin came with his ride on and cut the grass for us. Remarkable how quickly he did it. If only we could afford one just like his! Donations please!!

P1110285.jpg
He did the entire site, including field 2 in less than two hours!
By Alan Cooper
User avatar
g.89
Paid up Member
 
Posts: 654
Joined: Sun Jan 27, 2013 5:39 pm
Location: CRANSWICK

Re: Work in Progress

Postby g.89 » Sat Jul 29, 2017 7:36 pm

I wasn't idle. I applied wood preservative (2 coats) to the inside of VB3, ensured Brad's safety etc and with Chris's help removed one of the roof bands, prepared it and primed it (and then forgot to take a photo of it).
P1110276.jpg
Although the preservative is colourless you can see where your up to, until it dries.

I also spoke with three groups of visitors about our aims and objectives.

A good day!
By Alan Cooper
User avatar
g.89
Paid up Member
 
Posts: 654
Joined: Sun Jan 27, 2013 5:39 pm
Location: CRANSWICK

Re: Work in Progress

Postby g.89 » Sat Aug 19, 2017 9:07 pm

This week has seen highs and lows at Fimber Halt!

On Wednesday VB3 flooring was completed.
P1110394.jpg
A nice smooth floor.

However, it was noted that the newly painted interior walls have had their finish badly affected by water seeping through the timbers. With hind site we should have treated, re-caulked and painted the outside before doing the inside. To try and stop the rain getting onto the two ends so that they will dry out and can be dealt with, I erected some temporary shelter. I hope we don't suffer any high winds for a while!

P1110406.jpg
P1110407.jpg
Plastic sheeting and some sheets of ply to protect the wood


Refurbishing and rebuilding VB3 is proving to be a challenge!!
By Alan Cooper
User avatar
g.89
Paid up Member
 
Posts: 654
Joined: Sun Jan 27, 2013 5:39 pm
Location: CRANSWICK

Re: Work in Progress

Postby g.89 » Sat Aug 19, 2017 9:17 pm

On Saturday we had the esteemed presence of our chairman and site manager :P They busied themselves with cleaning newly acquired signalling stuff and preparing a site for moving the sleepers to. They are currently sitting at the end of the coach and we hope get some mechanical help to move them soon.

P1110396.jpg
Chairman Ed hard at it with a wire brush attachment.
P1110405.jpg
Site manager Keith hard at it with a spade.

Meanwhile one of our new volunteers, Barry did a lot of hard work filling in holes by the south gate in preparation for using it as the visitor entrance on Best of British day on the August bank holiday.

P1110399.jpg
This used to be one of Barry's holes.
By Alan Cooper
User avatar
g.89
Paid up Member
 
Posts: 654
Joined: Sun Jan 27, 2013 5:39 pm
Location: CRANSWICK

Re: Work in Progress

Postby g.89 » Sat Aug 19, 2017 9:23 pm

Last but certainly not least, Robin Bell gave field two a dressing with a 'drag' to smooth it and kill some weeds. The field is quite firm despite the heavy rain we have been having so we are confident that it will be an excellent car park.

P1110401.jpg
Life can sometimes be a drag!

P1110402.jpg
A bit of free advertising for Robin:)
By Alan Cooper
User avatar
g.89
Paid up Member
 
Posts: 654
Joined: Sun Jan 27, 2013 5:39 pm
Location: CRANSWICK

Re: Work in Progress

Postby chalkie » Sat Aug 19, 2017 9:52 pm

A few more photos of some of the S&T equipment we have recently acquired two Westinghouse circuit controllers
Attachments
20170819_164744.jpg
Ed Hague
User avatar
chalkie
Chairman
 
Posts: 1812
Joined: Sun Apr 18, 2010 5:00 pm

Re: Work in Progress

Postby 4008 » Sun Aug 20, 2017 9:57 am

Looks like a super day was had!
Matthew Brown
User avatar
4008
Membership, Media and Archive
 
Posts: 1977
Joined: Wed Dec 24, 2008 12:21 am

Re: Work in Progress

Postby g.89 » Thu Aug 31, 2017 10:12 am

Work on VB3 is progressing albeit at a painfully slow rate.
Yesterday saw the finishing touches being put to the floor by the addition of a skirting and work started on fitting steel plates to the outside to cover the gaps. Both were sealed up with silicone to make watertite. Also added was an aluminium step plate.

P1110524.jpg
A bit of skirting finishes the floor
P1110523.jpg
Steel plates seal the bottom of the van body
P1110526.jpg
A nice touch to the entrance
By Alan Cooper
User avatar
g.89
Paid up Member
 
Posts: 654
Joined: Sun Jan 27, 2013 5:39 pm
Location: CRANSWICK

Re: Work in Progress

Postby Turnip Town » Thu Aug 31, 2017 12:06 pm

Looking very good indeed. Many thanks to all volunteers concerned! :)
Ivan Merino
User avatar
Turnip Town
Secretary
 
Posts: 2562
Joined: Wed Dec 24, 2008 1:10 am